Future Aircraft Carrier (CVF)

Queen Elizabeth Class
 

Part 4

             Article Parts 

 1. Current Project Status and
     Graphics

  2. Specification

  3. The Project and its Origins

  4. Role

  5. Smart Procurement

  6. Project Schedule

  7. Procurement Process I
      (until Jan 2003)

  8. Procurement Process II  
      (until July 2007)

  9. Procurement Process III
      (latest situation)

10. Management and Industry
       Structures

11. Aviation Operations

12. STOVL or CV F-35?

13. Platform Design ...

14. ... and Redesign

15. C4ISR Facilities

16. Operational Concepts

17. Crew, Accommodation &
       Habitability

18. Propulsion and Engineering

19. Manufacture

20. Build Problems and UK
      Content

21. Basing and Support

22. Costs

23. Air Group

24. Aviation Requirements and
       Facilities

25. Catapults and Arresting Gear

26. Armament and Armour

27. Operations

28. Names

29. CVF Links



 

CVF Role

Strategic Defence Review (1998):  "aircraft carriers have wide utility, particularly for power projection and rapid deployment operations.”

Defence Strategic Guidance (2005):  "Carrier Strike is an expeditionary Fast Jet capability …… able to operate in uncertain Access Basing and Over flight conditions ……[to] deliver deep strike against Time Sensitive Targeting in all environments with its secondary role supporting the land component in Close Air Support and it will remain a robust Air Defence capability”.

The Invincible-class of carriers were designed for Cold War anti-submarine warfare operations, with an airgroup of mainly ASW helicopters plus a limited air defence capability provided by a small number of embarked Sea Harriers.  This essentially defensive role is no longer appropriate and the emphasis with the Future Aircraft Carrier (CVF) is now on increased offensive air power and an ability to operate a wider range of aircraft in a variety of roles.

The CVF mission statement has been officially defined: "The CVF is to be a joint defence asset with the primary purpose of providing the UK with an expeditionary offensive air capability that has the flexibility to operate the largest possible range of aircraft in the widest possible range of roles."

It is expected that CVF will be tasked:

  • As an early coercive presence that can promote conflict prevention through deterrence; 

  • As a flexible and rapidly deployable offshore base during expeditionary operations when airfields may be unavailable or denied, or when facilities ashore are still being established; and 

  • Contributing to the support of peacekeeping forces, and, when necessary, initiating offensive military action.    

 

jsf3.jpg (16572 bytes)
Lockheed JSF's fly over a Strike Carrier Task Group

Criticism

Despite the importance of CVF, the high cost of the project inevitably soon generated criticism and the tragic events of 11 September 2001 has sadly probably played a key role in saving it from cancellation.  The perceived success of the USN's carriers in the Afghanistan War of late 2001, and the associated limitations of the much smaller HMS Illustrious in the same action, greatly reinforced the governments commitment to CVF. 

On 22 November 2001 the Minister for Defence Procurement, Lord Bach, said: "The future carriers are very much a lynchpin of our planned defence capability and will greatly enhance our ability to intervene decisively in the world's trouble spots.  The value of such large carriers is being underlined on a daily basis by our American allies in operations over Afghanistan. That demonstration of power, reach, and strategic mobility of carrier-borne air power provides ample confirmation that our commitment to this project is the right way to go."  This conclusion was undoubtedly further reinforced by the achievements of USN carriers during the Gulf War II of March-April 2003, and the limitation of the RN's flagship aircraft carrier (HMS Ark Royal) to her secondary LPH role during the same conflict. 

Nevertheless, like a previous RN carrier project ( CVA-01), CVF become a very high-profile defence capital expenditure programme subject to much criticism, not least from Army and Air Force sources "off the record".  But perhaps surprisingly to many people, with an initial procurement cost projected to be in the region of £3.5 billion ($7 billion) for the two ships at current prices, CVF was actually very far from being the most valuable, e.g. the Joint Combat Aircraft Project will cost around £8bn to procure, and the Typhoon Eurofighter fighter a massive £19.7 billion to procure.  However the UK Defence Budget was under extreme pressure as the MOD had to meet the immediate operational demands of the conflicts in Afghanistan and Iraq , CVF was regarded by many people as one of the few  "big ticket" items that could be easily cancelled in order to relieve the pressure - partly because it was a national rather than multi-national project. 

Pressure on the project became intense and delays in announcements increased speculation that the project was doomed, in the amidst immense negative publicity it was something of a surprise when the project got Main Gate 1 approval in December 2005, and finally passed the critical Main Gate 2 milestone in July 2007 - nearly three years later than once hoped.

 

Key User Requirements

Nine top-level Key User Requirements (KURs) for CVF have been laid out, which define the capabilities required.  They are as follows:

  • KUR 1, Interoperability: CVF shall be able to contribute to joint/combined operations;

  • KUR 2, Integration: CVF shall be able to integrate with the joint battlespace to the extent required to support air group operations, command, control, communications, computers and intelligence (C4I) functions and survivability;

  • KUR 3, Availability: CVF shall be able to provide one operational and available platform at all times;

  • KUR 4, Deployability: CVF shall be able to deploy for operations worldwide;

  • KUR 5, Sustainability: CVF shall be able to sustain operations;

  • KUR 6, Aircraft operation: CVF shall be able to deploy offensive air power to the sortie-generation profile specified without host-nation support;

  • KUR 7, Survivability: CVF shall be able to achieve a high probability of survival;

  • KUR 8, Flexibility: CVF shall be able to operate the largest possible range of aircraft; and

  • KUR 9, Versatility: CVF shall be able to operate in the widest possible range of roles.

Each of these is supported in more detail by a series of so-called user requirements documents (URDs), and there are typically 10 of these per KUR. 

A solution is developed which meets each of these URDs but, almost invariably, the result is too expensive or too difficult to achieve. It is the responsibility of the IPT, in conjunction with the customer and the supply chain, to examine these capability requirements and seek a solution that would measure trade-offs, and meets the available budget.  This is necessarily an iterative and lengthy process, requiring both analysis and synthesis of a complex set of variables.  A few examples of the cost - capability trade-off's faced have entered the pubic domain:

KUR 1, Inter-operability: This capability is essentially the degree to which information can be generated, gathered, supplied, and distributed through a variety of national and multinational systems.  Such a capability may require an enhanced communication fit, radars, antennae, as well as complex distribution systems and the ability to integrate complex messages that the embarked staff can comprehend and issue the necessary commands.  The capabilities for trading are very wide including, for example, intensive manpower that might be required to operate and maintain the systems.

KUR 3, Availability: The CVF shall provide one platform at high readiness for its principal roles at all times. This one almost speaks for itself – but the trade-off considerations include the life of the vessel, on-shore maintenance requirements, hit reliability, system redundancy and readiness.  It also, of course, drove the need for two ships.  The carriers have an availability which is very similar to that of cruise ships – of about 300 days per year.

KUR 6, Aircraft operations: The physical size of the air wing, the volume of the hangar and the sortie generation rate – that is, the total number of aircraft flights per day – are major influences on the capability.  Perhaps less well understood are the demands of high sortie generation rates on weapon handling and spaces for weapon preparation, prior to their delivery to the aircraft.  Considerable modelling has been undertaken to optimise the ability to handle a large number of aircraft on the flight deck and in the hangar, and deliver weapons to them. Such modelling has inputs, for example, on the number and size of the aircraft lifts; the arming and refuelling positions, as well as related matters of provision of aircraft maintenance spaces, reading rooms, mission planning and so on.  The trade space is extensive.

KUR 8: Flexibility: This capability is virtually guaranteed with a ship of this size, with its flexibility to be reconfigured to operate different aircraft and to operate, for example, a landing platform helicopter role, similar to HMS Ocean, for humanitarian support.  Consideration was also given to fitting catapults and arresters, demanding space and power throughout the ship, to fit future systems, representing a huge area of potential trade-off.

 

Carrier Strike

CVF is actually only one part of the wider Carrier Strike requirement, four main four components go together to bring this joint force capability:

  • Joint Combat Aircraft (JCA), The UK is part of US Joint Strike Fighter programme
     
  • Maritime Airborne Surveillance and Control (MASC), Replacement for Sea King Airborne Surveillance and Control.   MASC will provide the air group with the tactical support in achieving the specified mission and will also deliver additional Situational Awareness to the Force.
     
  • Future Aircraft Carrier (CVF), An expeditionary airbase for strike operations
     
  • Maritime Afloat Replenishment and Support (MARS), Sea based support for CS, without MARS supplying bombs, fuel and stores Carrier Strike loses any ability to be expeditionary.

Carrier Strike will provide the UK with an expeditionary precision strike capability able to operate without the need for Access, Basing and Overflight facilities of any host nation.  The graphic above shows the top level view within the Architectural Framework (MODAF) which is being used to support the design process, and shows many of the Agencies and Organisations which CVF will need to interact with.

In December 2003 the MOD appointed a 'Senior Responsible Owner for Carrier Strike', Rear Admiral Nigel Guild - who was also Controller of the Navy and an Executive Director at the DPA . He was made personally responsible for ensuring the Carrier Strike programme meets its objectives and delivers the projected benefits. Admiral Nigel Guild considers himself to be "answerable but not accountable" for the delivery of the overall capability. His main responsibilities are to ensure that: the overall programme is coherent and has the right characteristics for success; the programme reflects departmental priorities and is worth pursuing;  the programme is subject to review at appropriate stages; oversight of the programme business cases; monitoring and driving progress; problem resolution and referral; benefits are delivered; and there is a post implementation review.

 